Storage Units
Location
Morwell, Victoria
Budget
$900,000
Completion Date
May 2023
Build Duration
24 weeks
Architects
Virtue Developments in-house Design and Construct
Client
Platinum Storage Solutions
The client brief was to build 88 modern individual storage units, ensuring they are:
- verman proof
- tamper proof
- and damp proof
Security at the site should include:
- speartop fencing
- camera system
- electric gates with digital access.
As a response to the brief, our team carefully planned the complete project from start to finish to successfully achieve the seven month construction time-frame
Alongside construction, other features completed were auto sensor lights to each unit and roller door seals.
To provide a seamless service for our client, we also took care of the landscaping and sign writing, and assisted with council town planning and engineered drainage.