Storage Units

Location
Morwell, Victoria

Budget
$900,000

Completion Date
May 2023

Build Duration
24 weeks

Architects

Virtue Developments in-house Design and Construct

Client
Platinum Storage Solutions

The client brief was to build 88 modern individual storage units, ensuring they are:

  • verman proof
  • tamper proof
  • and damp proof

Security at the site should include:

  • speartop fencing
  • camera system
  • electric gates with digital access.

As a response to the brief, our team carefully planned the complete project from start to finish to successfully achieve the seven month construction time-frame

Alongside construction, other features completed were auto sensor lights to each unit and roller door seals.

To provide a seamless service for our client, we also took care of the landscaping and sign writing, and assisted with council town planning and engineered drainage.